Thursday, November 19

Fresh Powder





While it rains like crazy outside (150mm in the last 24 hrs) it appears to be snowing in the workshop-garage.  The drywall crew has spent the last couple of days doing the final touch ups which involve lots of sanding as the pictures show.

Friday, November 13

Building Green (& Greene)






Following a very wet and windy night the morning actually began clear and sunny for Soenka and Devon to begin the first of 8 column bases.  In order to keep the mortar free from moisture, Karen has rigged a portable shelter to keep the columns protected during their construction.

Monday, November 9

Heat is ON!





A great day today as Stewart Reynolds, our heating installer arrived and flicked the main switch to get the boiler and pumps running.  Within a couple of hours you could feel the floor warming and watch the thermostats climb.  Meanwhile, our drywall mudder Dan spent  busy day taping and filling.

Thursday, November 5

Copper Flashing Installed




Wednesday afternoon was spent cutting and fitting the copper flashing around the base of the drip cap around the workshop-garage building.  Our roofer, Pat, had bent up some flashing from an old roll of copper that he'd had in his shop and it was very enjoyable to fit and install on what may have been the last sunny afternoon for some time. 

Tuesday, November 3

Drywall Delivery






The insulators finished today at 11:00 am exactly as promised, then the drywall arrived all pre-arranged for which part of the building it had to go into.  The truck crane operator hoisted it into the shop and garage doors but also up into the office area through the window which I had removed previously.  Complete delivery done in less than an hour with all sheets in pristine condition including the 14' ones in the upstairs office!  

Insulation done at 11:00, Drywall delivered by 1:00, Window nailed back in place by 2:00. Inspector arrives and completed the pre-drywall inspection by 2:30.  Drinking tea by 3:00...

Monday, November 2

Insulation In




The insulation crew arrived this morning at 7:15 and away they went getting all of the garage, office and celestory done with only the workshop to complete tomorrow.

Sunday, November 1

Preparing for a Busy Week Ahead






The coming week promises to be a busy one with George and Brent, our two plumbers here to complete the rough-in of the house plumbing.  

The insulation crew arrives Monday morning to start on the shop-garage building and the fibreglass batts are all ready for them, having been delivered last Thursday. 

The re-claimed fir that was being cleaned-up and planed in Nanaimo was delivered in two loads on Friday and today, as well.  Now we have to get busy to sand and apply finish to the underside, which will become the ceiling, then install it on the second floor of the house. 

A good chunk of Saturday (Halloween) was spent in my pressure washing costume washing the rocks (Cobble Hill cobbles) we've been gathering from all over the property in preparation for our stone mason Soenke Neilsen who also arrives Monday morning.